Message ID: 803     Entry time: Thu Aug 26 12:17:29 2021
Author: Eric Dufresne 
Type: 8-ID-E 
Category: Repairs 
Subject: Recent X-ray BPM results from 8ID-E, dip in current on center 
From: "Dufresne, Eric" <[email protected]>
Subject: Re: RFQ Request Argonne National Labs Quote # APS Dufresne m402 w. Coating & Adv
Date: August 26, 2021 at 11:39:35 AM EDT
To: Marychris Arcuri <[email protected]>

Hi Marychris,

can you please send this to your technical folks and ask them to get back to me?
The system I am using should still be under warranty.
I am having weird behavior with the inert gas unit, so I include
a report I wrote about the behavior.

Regards,
Eric

Fwd: RFQ Request Argonne National Labs Quote # APS Dufresne m402 w. Coating & Adv
Marychris Arcuri <[email protected]>
Thu 8/26/2021 10:48 AM
To: Martin, Benjamin W. <[email protected]>
Cc: Mark Katafiaz <[email protected]>; Dufresne, Eric <[email protected]>

1 attachments (2 MB)
July21-Report.pdf;

Hi Eric,
Your email has been received and I have included your technical point of contact on this email, Dr. Ben Martin.
Our team will review your report and reach out shortly.
Thank you,

Marychris Arcuri
Sydor Technologies
585.750.8578 | www.SydorTechnologies.com

RE: RFQ Request Argonne National Labs Quote # APS Dufresne m402 w. Coating & Adv
Valerie Fleischauer <[email protected]>
Thu 9/2/2021 12:52 PM
To: Dufresne, Eric <[email protected]>
Cc: Martin, Benjamin W. <[email protected]>; Marychris Arcuri <[email protected]>;
Matthew Zelazny <[email protected]>; Mark Katafiaz <[email protected]>

Hi Eric,

Thank you for sending along the report on the issue you are seeing with your diamond monitor. After looking through it we
have a few follow up questions (below) before making any conclusions. If it is easier and you are available for a call
next week to run through things please let us know.

  • The report mentions restarting the electrometer. What are the symptoms that drive the restart? i.e.
    software related crashes, or testing to see if this changes the diamond behavior
  • Has anything changed in the test setup or analysis since March? Or since the diamond was first installed?
  • Are all components in the inert gas purge UHP rated? Including tubing, regulator, etc.

Thank you,

Val

Val Fleischauer, Ph.D.
Technology Development Scientist, Sydor Technologies
1.585.278.1168 | www.SydorTechnologies.com

Re: RFQ Request Argonne National Labs Quote # APS Dufresne m402 w. Coating & Adv
Dufresne, Eric <[email protected]>
Fri 9/3/2021 3:43 PM
To: Fleischauer, Valerie E. <[email protected]>
Cc: Martin, Benjamin W. <[email protected]>; Marychris Arcuri <[email protected]>;
Matthew Zelazny <[email protected]>; Mark Katafiaz <[email protected]>

Valerie, all in cc,

I've found the electrometer not as stable as I would have expected. I've had to power cycle it sometimes few times a week to get
reliable signals. I don't have any error logs to report, but I'll make a table below of my observations in July.
Not very detailed, sorry.

Nothing changed since March, but some mechanical mounting. In March I changed motorized stages under it.

The BPM is always under N2 flow (High Purity Grade), and with the recommended flow.

Eric

7/13 Had to restart twice to remove large background currents of 11 uA. X-ray total current ~ 100nA.
7/19 Rebooted EM after end of experiment after noting dark currents were high.
7/23 BPM/EPICS not running. Did reset


Repair report link below:


https://anl.box.com/s/daq73cgioh6iqcxmcidoko4m9gvhvw5x

IEMR Report for M402 DBPM S/N: 017
Matthew Zelazny <[email protected]>
Wed 10/27/2021 9:41 AM
To: Dufresne, Eric <[email protected]>
Cc: Martin, Benjamin W. <[email protected]>; Marychris Arcuri <[email protected]>;
Fleischauer, Valerie E. <[email protected]>; Ziegler, Raymond <[email protected]>;
Mark Katafiaz <[email protected]>

Eric,

Attached is the IEMR report for you device. As you will see from the report the metallization of the sensor has been compromised.
Contamination in the operating environment is the suspected cause of the performance degradation.
Our recommendation is to replace the diamond and requalify the device.

Let us know how you wish to proceed.

Regards,

Matt

Confirmation of our conversation on DBPM
Rob Littlewood
Wed 11/24/2021 6:16 AM
To: Dufresne, Eric <[email protected]>
Cc: Mark Katafiaz ;Marychris Arcuri

Hi Eric,

This mail is just to confirm what we discussed last week; i.e. we will go ahead and replace the diamond in
your device for you for the lower fee of the quoted inspection and minor repair.

We will also provide updated information advising the use of He gas and let you know about any other pertinent
points to be observed when spec’ing other parts of the gas delivery system.

Kind Regards

Dr Rob Littlewood

Sydor Technologies
+44 (0)7917 567785
Skype: live:r.littlewood_1

Re: Confirmation of our conversation on DBPM
Dufresne, Eric <[email protected]>
Wed 11/24/2021 10:32 AM
To: Rob Littlewood <[email protected]>
Cc: Mark Katafiaz <[email protected]>; Marychris Arcuri <[email protected]>; Narayanan, Suresh <[email protected]>
Bcc: Ziegler, Raymond <[email protected]>

Thank you Rob,

you can count on me to get back to Sydor after the summer run of 2022 with any performance issue.
Helium makes sense too. I would appreciate getting an estimate of when I will get the repaired BPM back.

Happy Thanksgiving,

Eric



4/8/2022



Last week, I received the new Sydor X-ray BPM.
It is S/N 17, and its performance is attached in att. 2.
It was shipped around March 30, and arrived on site on Friday April 1.
I got it on my return to work from vacations.
Attachment 1: July21-Report.pdf  1.824 MB  Uploaded Thu Aug 26 13:18:34 2021
Attachment 2: SydorQAtesting-041222-4285_001.pdf  99 kB  Uploaded Tue Apr 12 16:14:30 2022